Current and Recent Projects
| | Tank and Building Demolition - Macon, GA | | Completed April 2007 |
| Description: Demolish a 5800 square foot brick warehouse. Remove concrete foundation. Grade and seed. Remove miscellaneous pipe lines, equipment and above ground storage tanks. Lead abatement. Contract value: $130,000 |
|
| | Chemical Plant Demolition and Renovation - Brunswick, GA | | Completd September 2007 |
| Demolish 16 buildings with total 43,000 sqft. Remove and recycled concrete foundations and footings. Grade and seed. Remove 3600’ of overhead pipe lines and support piers. Remove 36 large (100,000 gallon+) above ground storage tanks. Remove 3.5 miles of rail track, ties and ballast. Toxaphene hazardous remediation.Miscellaneous drainage, clearing, and tank cleaning projects. Recycled 12,000 tons of concrete recycled. Contract value: $648,000. |
|
 | | Chemical Plant Demolition and Renovation - Hattiesburg, MS | | Completed Dec 2007 |
| Demolish buildings and warehouses with total 76,000 sqft. Remove concrete foundations and footings. Remove 3600’ of overhead pipe lines and support piers. Remove above ground storage tanks. Remove two large boiler installations. Remove 1.5 miles of rail track, ties and ballast. Recycled 70,000 tons of concrete and 250,000 tons of metals. Asbestos abatement and hazardous materials abatement. Miscellaneous drainage, clearing, and tank cleaning projects. Contract value: $795,000.
|
|
 | | Concrete Crushing and Recycling - Pass Christian, MS | | Completed September 2007 |
| Break up, crush, recycle and market approximately 60,000 tons of concrete debris collected from Hurricane Katrina destruction. Contract value $1,100,000 |
|
 | | Walgreeens - Gautier, MS | | Completed April 2007 |
| Demolish bank building and outbuildings. Remove and disposed of concrete foundations and footings. Site Prep and Drainage. Contract value: $115,000. |
|
 | | Newman Lumber Yard Project - Gulfport, MS | | Completed August 2008 |
| Commercial Demolition of 7 warehouses which included the recycling of approximately 25,000 tons of concrete and the remediation of contaminated soil. Site prep and drainage for a future 85 acre commercial development. Contract Value $256,000.00 |
|
 | | Chang Commercial Devlopments - Gulf Coast, MS | | Completed September 2008 |
| Cleared and grubbed 7 Commercial Development sites. Approximately 10,000 tons of concrete to be recycled. Site preparation and drainage for further development. Soil remediation. Contract Value $47,000.00 |
|
 | | General Electric Water - Port Gibson, MS | | Completed August 2008 |
| Extraction, Dismantlement, and Demolition of 2 water treatment trailers used to supply the Grand Gulf Nuclear Power plants water needs. Contract Value $85,000.00 |
|
 | | Stennis Airport - Bay St. Louis, MS | | Completed November 2008 |
| Bonded drainage improvement project. Delivered to client 30 days ahead of schedule.Contract Value $260,000.00. |
|
 | | Paladine Resort Project - Biloxi, MS | | Completed January 2009 |
| Demolition of 56,000 sq. ft. of retail development. Asbestos remediation and 15,000 tons of concrete recycled. Contract Value $85,000.00 |
|
 | | Coast Electric Substation - Pass Christian, MS | | Completed July 2009 |
| Cleared and Grubbed approximately 4 acres and built a foundation for Substation. Contract Value $65,000.00 |
|
 | | Stennis Space Center Amunition Plant Restoration - Stennis Space Center, MS | | Completed December 2009 |
| Cleaning and Washing of pits and trenches at the former ammunition plant to prepare them for filling and concrete cap. Contract Value $550,000.00 |
|
 | | Keesler Air Force Base Boiler Demo - Biloxi, MS | | Completed September 2009 |
| Industrial Demolition of an original boiler house and 100 ft brick stack. Project completed 7 days ahead of schedule. Project Cost $98,500.00 |
| |