Current and Recent Projects
| | Tank and Building Demolition - Macon, GA | | Completed April 2007 |
| | Description: Demolish a 5800 square foot brick warehouse. Remove concrete foundation. Grade and seed. Remove miscellaneous pipe lines, equipment and above ground storage tanks. Contract value: $130,000 |
|
| | Chemical Plant Demolition and Renovation - Brunswick, GA | | Completd September 2007 |
| | Demolish 16 buildings with total 43,000 sqft. Remove concrete foundations and footings. Grade and seed. Remove 3600’ of overhead pipe lines and support piers. Remove 36 large (100,000 gallon+) above ground storage tanks. Remove 3.5 miles of rail track, ties and ballast. Miscellaneous drainage, clearing, and cleaning projects. Contract value: $648,000. |
|
| | Chemical Plant Demolition and Renovation - Hattiesburg, MS | | Completed Dec 2007 |
| | Demolish buildings and warehouses with total 76,000 sqft. Remove concrete foundations and footings. Grade and seed. Remove 3600’ of overhead pipe lines and support piers. Remove above ground storage tanks. Remove two large boiler installations. Remove 1.5 miles of rail track, ties and ballast. Miscellaneous drainage, clearing, and cleaning projects. Contract value: $595,000.
|
|
 | | Concrete Crushing and Recycling - Pass Christian, MS | | Completed September 2007 |
| | Break up, crush, recycle and market approximately 60,000 tons of concrete debris collected from Hurricane Katrina destruction. Contract value $1,100,000 |
|
| | Walgreeens - Gautier, MS | | Completed April 2007 |
| | Demolish bank buildings and outbuildings. Remove concrete foundations and footings. Site Prep and Drainage. Contract value: $115,000. |
|
| | Newman Lumber Yard Project - Gulfport, MS | | In Process |
| | Commercial Demolition of 7 warehouses which will include the recycling of approximately 25,000 tons of concrete and the remediation of contaminated soil. Site prep and drainage for a future 85 acre commercial development. |
|
| | Chang Commercial Devlopments - Gulf Coast, MS | | In Process |
| | 7 Commercial development sites to be cleared and grubbed. Approximately 10,000 tons of concrete to be recycled. Site preparation and drainage for further development. |
|
 | | General Electric Water - Port Gibson, MS | | Completed August 2008 |
| | Extraction, Dismantlement, and Demolition of 2 water treatment trailers used to supply the Grand Gulf Nuclear Power plants water needs. |
| |